Rhodes Avenue Updates

Rhodes Ave is temporarily closed to through traffic due to construction. Alternate routes are advised!

• The channel from Ute Street south to end of project has been shaped and is nearly complete. Final seeding and installation of stabilization matting will be completed on Monday, April 18, 2022.
• Ute St and Rhodes: Concrete box culvert is under construction.  Floor poured on Thursday, April 14, 2002 and should be complete in approximately two (2) weeks. Once complete, construction of concrete box culvert at Spartan Drive will be constructed
• Irrigation improvements are underway beginning at Ute Street and continuing north along Rhodes Avenue.
• The drainage channel south of Ute is being shaped and the concrete reinforcement mat will be installed during the week of April 18th.
• Work will continue to advance north along the drainage channel.
UTILITIES:
• Sewer main has been replaced from the Ute intersection all the way to Sierra Court. 
• Sewer manhole at Sierra Court will be replaced next week and sewer work will continue towards White Pine and Countryside Court.
• Sewer, gas, and water lowerings to accommodate the new box culverts have been completed at Ute St and Spartan Drive.
• Power, telephone, and cable are being relocated as needed along the project.

Current photo of Rhodes Avenue.Photo of the box culvert floor being poured on April 14, 2022. The walls should be poured the week oCurrent photo looking South from Ute Street.The intersection of Ute and Rhodes. The structure on the right will be a new concrete box culvert on

Facebook Twitter Email

Other News in City Notices & Updates

Hike With A Paleontologist!

Posted on: May 11, 2022
Night of a Thousand Heroes Event Flyer

Night of a Thousand Heroes

Posted on: April 29, 2022
Water Color Class Flyer

Watercolor Class at the Library

Posted on: April 29, 2022

CCPD First Annual Golf Tournament

Posted on: April 20, 2022

UTV Discussion

Posted on: April 15, 2022
Headstone

Lakeside Cemetery Clean Up Week

Posted on: April 14, 2022
construction notice

2A Notice of Construction

Posted on: April 11, 2022
East Ridge Campground RV Tent Site Photo

Campground Reservations

Posted on: April 8, 2022

150th Sesquicentennial Proclamation

Posted on: April 6, 2022
Trails Policy Committee Announcement

New Trails Policy Committee

Posted on: April 5, 2022
District 2 Announcement

Open District 2 City Council Seat

Posted on: April 5, 2022

Request for Proposals

Posted on: April 4, 2022

Pothole Repair Requests

Posted on: March 31, 2022
Cribbage Club Event Flyer

Cribbage Club

Posted on: February 7, 2022
Story Swap Book Club Flyer

Story Swap Book Chat

Posted on: February 3, 2022
Canon City 150th logo

Cañon City’s Sesquicentennial

Posted on: January 26, 2022

Business Licensing

Posted on: December 16, 2021

Fence Repair Permit Amnesty

Posted on: December 16, 2021