2A Raynolds/Pear/Field Project Construction

Pyramid Construction will begin road construction on the 2A Raynolds/Pear/Field Project on Monday, May 8, 2023.

During the first part of next week, erosion control will be set up in addition to the removal of curb and gutter. This work will start at the southern end of Raynolds Avenue near Fremont Drive and move north. During this time the water main crew, KR Swerdferger, will continue their work near the northern end of Raynolds Avenue from Cherry Street to Pear Street. 

Road closures and detours will remain the same that have been in place during the water main work. Raynolds Avenue will be closed to thru traffic and at least one lane will remain open for local residential and emergency traffic.

Work on the entire project is expected to take 120 days to complete, setting the anticipated completion in early September. The entire project includes all of North Raynolds Avenue, plus Pear Street from Field Avenue to Raynolds Avenue, and Field Avenue from Pear Street to Central Avenue. 

For more information, please visit the city’s website at https://www.canoncity.org/2A or contact City Public Works Director, Leo Evans, at laevans@canoncity.org.

Facebook Twitter Email

Other News in City Notices & Updates

Photo of pickleball courts

Pickleball Community Interest Inquiry

Posted on: September 21, 2023
Photo of Arkansas River, river rocks, trees lining the river bank, and a mountain in the background

National Pollution Prevention Week

Posted on: September 18, 2023
construction notice

NOTICE OF CONSTRUCTION: Alley Pavement

Posted on: September 15, 2023

Community Agency Funding

Posted on: September 13, 2023

Paper Shredding Event

Posted on: September 11, 2023
Red Color Block with white heart beat running across and text info about Oct 5 Blood Drive

Blood Drive

Posted on: August 10, 2023

Deer Harvesting Program Inquiries

Posted on: August 9, 2023

Records Requests

Posted on: June 13, 2023