Resurfacing work will occur on Esplanade Court (Phay to Bauer), Four Mile Parkway (US-50 to CR-123), and Oak Avenue (10th to Yale) during the weeks of April 22nd and April 29th.
Esplanade Court (Phay to Bauer)
Concrete work is expected to be complete early next week. Paving is planned for later in the week of April 22nd.
Four Mile Parkway (US-50 to CR-123)
Resurfacing work is currently planned for the week of April 22nd and is expected to take approximately five (5) days to complete. Traffic will be maintained for a majority of the work via flaggers with access to Love’s maintained from US-50 during the work. See map below.
Oak Avenue (10th to Yale)
Concrete work is planned to begin the week of April 22nd with paving work planned to begin the week of April 29th. Work is expected to be completed by the end of the week of April 29th or early the following week.